Not post in a while - thats because not much has happened really. We should have all documents the Certifier needs to start the construction process by end of next week - just waiting on a document from the building designer showing DA condition references and a document from the engineer stating structural stability of existing party walls. Hopefully start to demo start of next month! In other DA news - the council has requested a landscape plan by a qualified landscape designer, a swept path analysis and amended roof plans to minimise neighbour over shadowing. The proposed studio above garage blocked out too much light apparently. So far ive organised a landscaper to start on a design, had a swept path analysis done and will discuss on weekend with builder as to best garage attic roof option. Should get all this back to council in 2 to 3 weeks’ time- then council can assess the DA So we should have all documents the Certifier needs to start the construction process by end of next week - just waiting on a document from the building designer showing DA condition references and a document from the engineer stating structural stability of existing party walls. Hopefully start to demo start of next month!
In other DA news - the council has requested a landscape plan by a qualified landscape designer, a swept path analysis and amended roof plans to minimise neighbour over shadowing. The proposed studio above garage blocked out too much light apparently.
So far ive organised a landscaper to start on a design, had a swept path analysis done and will discuss on weekend with builder as to best garage attic roof option.
Should get all this back to council in 2 to 3 weeks’ time- then council can assess the DA
No comments:
Post a Comment